Work on the Phase 2 Environmental Site Assessment
(“ESA”) process for the Sydney Steel site began in February
2003, immediately following submission of the Final Phase 1 ESA
Report (SEACOR Environmental Inc.) in January 2003.
A Phase 2 ESA involves collecting soil and water samples in order
to determine if environmental contaminants are present. Based on
the findings of the Phase 2 programs, further work (“Phase
3”) may be done to gather more information on any areas of
interest.
Four areas of the site have undergone Phase 2 & 3 ESAs to date,
and another three programs will be carried out in the future to
cover the remainder of the site. The areas covered to date are as
follows: (A brief summary of each program can be accessed via the
following links )
Victoria Road/Maintenance Shops
Area
High Dump/Slag Stockpiles Area
Blast Furnace Stockyard/No. 1
& 2 Piers Area
Bar Mill and Mobile Shop Areas
Blast Furnace Area
These areas cover the SYSCO site from the Victoria Road Overpass,
around the south end of the site, along the east shore of Muggah
Creek (including the slag piles), and around the north end of the
site to the International Piers. The middle part of the site (where
the rolling mills and steel shops were located) has not yet been
assessed.
For some of these areas, both Phase 2 and Phase 3 have been completed,
and SYSCO is preparing to address issues identified through the
course of the studies. Significant dates for each program are provided
in the following table:
| Area |
High Dump/
Slag Stockpiles |
BF Stockyard/No. 1 & 2 Piers |
Victoria Road/Maintenance Shops |
Bar Mill and
Mobile Shop |
Blast Furnace
Area |
Steel Shop Area |
| RFP Issued |
April 3, 2003 |
May 8, 2003 |
June 12, 2003 |
Oct. 31, 2003 |
May 9, 2005 |
March 21, 2006 |
| Contract Awarded |
May 8, 2003 |
June 4, 2003 |
July 9, 2003 |
Nov. 17, 2003 |
June 2005 |
|
| Consultant |
MGI Limited |
AMEC Earth & Environmental |
Dillon/ADI |
ADI Limited |
Amec Earth & Environmental |
|
| Phase II ESA |
| Field Work Started |
May 2003 |
July 2003 |
August 2003 |
Nov. 2003 |
July 2005 |
|
| Final Report Issued |
Oct. 2003 |
Feb. 2004 |
March 2004 |
July 2004 |
March 2006 |
|
| Phase 3 ESA |
| Field Work Started |
Dec. 2003 |
Nov. 2003 |
May 2004 |
July 2004 |
|
|
| Final Report Issued |
April 2004 |
May 2004 |
January 2005 |
February 2005 |
|
|
|