|
PREFATORY NOTE
|
|
| |
During the review period for this report, significant
progress has been made in the effort to decommission and remove
buildings and wastes at the former Sydney Steel Plant. The following
summary serves as an update of the information contained in this
report as it relates to potential environmental issues associated
with various buildings and structures on the site.
|
|
| |
Summary of Environmental Decommissioning and Demolition
Sydney Steel Corporation February through December 2002:
|
|
| |
No.
2 Open Hearth (SCU 17)
Between November 2001 and March 2002, all but the southern portion
(approximately 100 metres) of the No. 2 Open Hearth Building (BD1)
was demolished. SEACOR prepared an Environmental Decommissioning
Plan for the structures, and all required decommissioning actions
were completed prior to demolition. Demolition of the remainder
of the building is planned for early 2003.
|
|
| |
Blast
Furnace Area (SCU 19)
Between March 2002 and May 2002, several buildings in the Blast Furnace
Area were demolished. These included the Turbo Blowers building (BD
78), the blast furnace Clarifier (BD 80) and four additional buildings
(BDs 79, 81, 81A and 87). All environmental decommissioning actions
were completed prior to demolition.
In September 2002, four Bunker ‘C’ tanks were cleaned
and removed from the south side of the ‘D’Boiler (“Boiler
Extension” - BD 73). In addition, a hazardous materials survey
of the ‘D’ Boiler building was conducted. SEACOR prepared
an Environmental Decommissioning Plan for the structure, and all required
decommissioning actions have been completed with the exception of
the removal of exterior asbestos-containing panels, which is currently
underway. Demolition of the building is planned for December-January.
The No. 3 and 7 Blast Furnaces (BD 70 and BD 82) were demolished in
May through July 2002. SEACOR prepared an Environmental Decommissioning
Plan for the structures, and all required decommissioning actions
were completed prior to demolition, with the exception of a layer
of asbestos insulation that was subsequently collected and disposed
at approved locations. Demolition of the aboveground concrete foundations
is planned for late 2003.
|
|
| |
Nos.
1 & 2 Piers Area (SCU 20)
Between March 2002 and May 2002, several buildings in the Blast Furnace
Area were demolished. These included the Docks Offices building (BD
86) and a small out building (BD 86A). SEACOR prepared an Environmental
Decommissioning Plan for the structures, and all required decommissioning
actions were completed prior to demolition. In addition, several large
piles of creosote timbers were processed and removed to the CBRM landfill
for disposal during the Spring of 2002.
|
|
| |
Rail
Finishing Mill (SCU 13)
Demolition of the Rail Finishing Mill buildings (BD 19) commenced
in October 2002, beginning with the 6/7/8 Bay portion. The 8 Bay Extension
(BD 19A) was retained for future use. The majority of the 6/7/8 Bay
building has been removed, and demolition of the 5 Bay building began
on December 4, 2002. SEACOR prepared an Environmental Decommissioning
Plan for the structures, and all required decommissioning actions
were completed prior to demolition.
|
|
| |
Universal
Mill Complex (SCU 15)
Demolition of the Old Rail Mill (BD 13), Old Motor House (BD 11f),
Old Reheat Furnace (BD 11g) and three other out buildings (BDs 11c,
11d, and 11e) was completed between April and July 2002. SEACOR prepared
an Environmental Decommissioning Plan for the structures, and all
required decommissioning actions were completed prior to demolition.
Demolition of the Northern portion (approximately 100 metres) of the
Axel Conditioning Building (BD 15) was completed in September 2002.
SEACOR prepared an Environmental Decommissioning Plan for the structure,
and all required decommissioning actions were completed prior to demolition.
|
|
| |
Liquid
Air Plant (SCU 10)
Demolition of the vertical oxygen tank located to the south of the
Liquid Air Oxygen Plant (BD 49) was completed in September and October
2002. SEACOR prepared an Environmental Decommissioning Plan for the
structure. |
|
| |
High
Dump and Central Slag Disposal Area (SCUs 26 & 27)
Between May and October 2002, a surface debris cleanup program was
carried out over much of the High Dump area. Activities included the
removal of empty storage tanks and other metal debris that had been
disposed of at the High Dump, the collection and removal of wood debris
and solid waste, and the grading of various areas. Any oils or hazardous
wastes encountered during the cleanup operations were taken to the
Brick Shed for temporary storage prior to disposal off site.
|
|
| |
Nos.
3 & 4 Piers Area (SCU 29)
Between May and August 2002, a surface debris cleanup program was
carried out over much of this area. Activities included the removal
of metal debris and piles of bulk materials such as slag and sintering
fines.
Demolition of the Transfer Building (BD 30) took place in August 2002.
Demolition of the North Crane took place on November 13, 2002. SEACOR
prepared Environmental Decommissioning Plans for both structures,
and all required decommissioning actions were completed prior to demolition.
|
|
| |
Tank
Farm (SCU 32)
Asbestos-containing insulation was removed from piping in the Tank
Farm (BD 88) early in the summer of 2002. Removal of waste materials
from the storage tanks in the Tank Farm compound began in August 2002.
With the onset of winter, the removal and processing of wastes has
been suspended until the spring. In the interim, a large amount of
water and fuel was treated and disposed of off site.
|
|
| |
Asbestos
Debris Area (SCU 34)
In the spring and summer of 2002, additional materials were added
to the asbestos-containing debris disposal area. Materials included
metal siding with an asbestos-containing coating and a mixture of
brick and asbestos insulation from four of the eight blast furnace
stoves. All materials were placed in lifts (layers) and each lift
was covered with a layer of soil. A final layer of soil was placed
over the entire disposal area in July 2002.
|
|