Demolition is complete on the Sysco site. The demolition
was on time and on budget. Murray
Demolition was main contractor on the project. Considerable
activity has been taking place with former steelworkers employed
on site, doing essential demolition activities and clean up. The
Demolition Gallery and Video
Gallery host interesting pictures and footage of the plant's
demolition.
There is a detailed decommissioning process, which must take place
before a building can be demolished. This includes a careful inspection
to ensure that all environmental and safety matters are dealt with
prior to the commencement of any demolition activity. Each building
must be evaluated and signed off by Seacor Environmental before
demolition takes place.
At this point, twenty-five buildings and structures have been removed,
including the machine shop, calcite plant, and old roll shop. Below
is a list of the structures that have been removed and the date
they were cleared for demolition to start. Other buildings will
be maintained for use in the planned industrial park. (Click on
the links below to see a picture of the demolition)
| BUILDINGS (click to view photos) |
RELEASE DATE |
VIDEO CLIPS |
| |
|
|
| Calcine Plant |
August 2001 |
|
| Ore Terminal Building |
August 2001 |
|
| Tie Plate Building |
August 2001 |
|
| Old Yard Office Building |
August 2001 |
|
| Open Hearth Furnace Stacks |
August 2001 |
|
| Ingot Stripper Craneway |
August 2001 |
|
| Mobile Building |
August 2001 |
|
| Boiler Shop, Electrical Repair Shop &Forge |
September 2001 |
|
| Machine Shop |
September 2001 |
|
| No. 2 Open Hearth Building |
October 2001 |
|
| Docks Office and Outbuilding |
February 2002 |
|
| No.
3 Blast Furnace and Stoves / No. 7 Blast Furnace Stoves |
February 2002 |
|
| No.
7 Blast Furnace Stoves |
February 2002 |
|
| Turbo Blower Building |
March 2002 |
|
| Old Rail Rolling Mill |
May 2002 |
|
| Old Power House |
May 2002 |
|
| Old Reheat Furnace |
May 2002 |
|
| East Perimeter Piperack |
May 2002 |
|
| Docks Ore Transfer House |
June 2002 |
|
| Oxygen Tank |
August 2002 |
|
| Bloom Mill Building - Axle Conditioning Area |
August 2002 |
|
| Rail Finishing Mill No. 6, 7 & 8 Bays |
October 2002 |
|
| Wellman
Crane - No. 3 Pier |
November 2002 |
|
| Rail Finishing Mill, No. 5 Bay |
November 2002 |
|
| "D"
Boiler Building |
November 2002 |
|
| Old Roll Shop |
December 2002 |
|
| Mackie Tanks |
February 2003 |
|
| Hospital
Building |
March 2003 |
|
| No. 3 Blast Furnace Bases |
August 2003 |
|
| NW
Bulk Fuel Storage Tank |
September 2003 |
|
| Electrical
Substation Frame |
October 2003 |
|
| Oxygen Tank External Structures |
November 2003 |
|
| SW Bulk Fuel Storage Tank |
December 2003 |
|
| Rail Finishing Mill Seven Bay |
May 2004 |
|
| Harbour Pumps |
May 2004 |
|
| #3 Power House |
July 2004 |
|
| EAF Scrap Bay |
August 2004 |
|
| NE Bulk Fuel Storage Tanks |
August 2004 |
|
| Mold and Zone Building |
August 2004 |
|
| Blooming Mill Motor Room |
September 2004 |
|
| Blooming Mill |
September 2004 |
|
| Reheat Furnace Building |
September 2004 |
|
| East Perimeter Pipe Rack |
October 2004 |
|
| Castor Water Treatment Plant |
October 2004 |
|
| 7th Bay Rail Finishing Mill |
November 2004 |
|
| Meltshop/Caster Building |
December 2004 |
|
| Scrapyard Crane and Runway |
January 2005 |
|
| SE Bulk Fuel Storage Tank |
January 2005 |
|
| Universal Mill |
January 2005 |
|
| U Mill |
February 2005 |
|
| No. 2 Powerhouse |
March 2005 |
|
| Electric Substation |
April 2005 |
|
| Brickshed |
April 2005 |
Demolition
Complete! |
|