Sydney Steel Corporation Business Plan 2005-06 (continued)
Performance in Prior Year
This section outlines stated goals and corresponding results for
each of the Corporations’ six core business areas, as per
their 2004-2005 business plan.
Demolition
- Stated Goal – Demolition to be 80 per cent to 90 per cent
completed by March 2005.
- Result – Despite several delays by Zoom Developers, demolition
is approximately 95 per cent complete.
- Stated Goal – Remaining structures will be assessed for
their ultimate removal or re-use in the new site redevelopment
plan.
- Result – Structures have either been demolished, scheduled
to be demolished, or slated for development for re-use.
Local Labor and Supplies
- Stated Goal – Maximize use of local labor for
Sysco projects.
- Result – Over 310,000 of person hours used in
2004-2005
- Stated Goal – Continue practice of using local supplies
and services whenever possible and feasible.
- Result - $3 million in local supplies and labor have been sourced
for the year ending March 31, 2005.
Liquidation of Major Equipment, Scrap, and Slag
- Stated Goal – Remove Electric Arc Furnace in 2004.
- Result – Electric Arc Furnace was removed in November,
2004.
- Stated Goal – Harvest scrap metal for future sale.
- Result – Approximately $948,000 in scrap sales was totaled
for fiscal 2004-05. Approximately 26,000 tonnes remain with an
approximate value of $6 Million based on current market conditions.
- Stated Goal – Reach slag sales for 2004-05 of more than
100,000 tonnes.
- Result – Final sales will be approximately 50,000 tonnes.
We have commissioned two studies to test value-added alternatives
for slag in order to increase sales. Potential applications are
in septic bed use and in the making of cement and concrete.
Site Redevelopment
- Stated Goal – Re-open the West Bridge by November 2004.
- Result – Bridge opened in November 2004.
- Stated Goal – Complete new access road (Spar Road) to
Whitney Pier and Sysco Site.
- Result – Road opened in January 2005.
- Stated Goal – Complete plans for the greening project
for the area adjacent to Sysco site and the Sydney Ports Access
Road.
- Result – With consultation with the community,
the Whitney Pier Historical Society acted as co-ordinator and
determined that developing a walking trail on this area would
be the best approach. The Corporations have assisted the society
with the creation of a plan for its implementation.
Environmental Remediation
- Stated Goal – Develop an environmental management plan
(EMP) for the High Dump area.
- Result – Complete.
- Stated Goal – Develop an EMP for the Blast Furnace and
Stock Yard area.
- Result – Complete.
- Stated Goal – Complete environmental site assessments
on area adjacent to Victoria Road overpass.
- Result – Phase II and Phase III work is complete.
- Stated Goal – Complete environmental site assessments
on administration building area.
- Result – Phase II and phase III work is complete.
Additional Plans
- Stated Goal – Conduct cleaning and demolition of the two
remaining 2.5 million gallon oil tanks.
- Result – Both tanks have been cleaned and demolished.
- Stated Goal – Remove and dispose of an estimated 50,000
kg of PCB’s.
- Result – Complete.
- Stated Goal – Remove and clean 2km of old oil
and tar lines.
- Result – 2 km removed and cleaned.
- Stated Goal – Remove and dispose of remaining asbestos.
- Result – Complete.
|